Cells in at one end, tested packs off the other — one takt across both segments +86 15327155363 sales@batterylinepro.com

Busbar laser welding / BLP-W6 — module segment, station 13 of 17

Four Figures Are Published for a Busbar Weld. Only Two of Them Are Criteria.

6 kW, 50 to 100 mm/s, fusion at least 1.0 mm deep and 1.5 mm wide, and a joint that holds 1000 N. This page says which of those your inspector can hold us to, and how.

⚠️ A pull test destroys the joint it proves. What a line running at takt does about that is section 06 — and it is the reason this page exists.

What this station promises

  • Told where the joint is — it does not go looking for it
  • Welded in line, at line takt — the module never leaves its carrier
  • Proved by a test that consumes the joint — so sampling is written, not assumed
  • 6 kWLaser source
  • 50–100 mm/sWeld speed
  • ≥1.0 mmFusion depth
  • ≥1000 NJoint pull strength

Station thirteen of seventeen, and it inherits almost everything

A busbar welder is bought as a machine and lives as a station. What arrives at it has already been decided by three stations upstream, and the welder cannot argue with any of them.

0102030405060708091011121314151617

Module segment · station 13 of 17 — busbar laser welding

  • 11Terminal addressing and laser cleaning
  • 12CCS and busbar plate fitting
  • 13Busbar laser welding — this stationYou are here
  • 14Post-weld cleaning and inspection
  • 16Module end-of-line test
Cells arrive Stack pressed Busbar welded — here Module tested
Gantry-framed welding cell over a module assembly line
Rendering — the module segment
In-line welding station with its enclosure closed
Rendering — welding in line, not off it
Finished prismatic module leaving the segment
Rendering — where our scope ends

A weld you can see and a weld that holds are separated by one millimetre of metal nobody can look at.

Depth

At least 1.0 mm of fusion below a surface you cannot inspect.

Width

At least 1.5 mm across the joint, which you can.

Strength

At least 1000 N — and finding out costs you the module.

The four figures we publish, and what each is a criterion for

⚠️ Two of them describe the machine and two describe the joint. Reading a machine figure as a quality figure is the commonest way a welding quotation gets oversold.

FigureWhat it is a criterion for
6 kWLaser source Nothing about your joints. It is capability, and its value to you is the margin left over when your busbar is thicker or your material more reflective than the blueprint one. Section 11 →
50–100 mm/sWeld speed A window, not a setpoint. Where inside it your joint runs is settled with your busbar material and section, and a supplier who names one number before seeing them has named it for somebody else's module. Section 07 →
≥1.0 mm / ≥1.5 mmFusion depth and width The per-joint criterion. This is the pair an inspection procedure is written against, because it can be checked on the joints that stay in the module. Section 07 →
≥1000 NJoint pull strength The joint criterion buyers trust most and can afford least often — the measurement destroys the joint it measures. Section 06 →
Two of the four are ours to hold. Geometry and pull strength are acceptance criteria; power and speed are the settings that produce them. A quotation that leads with kilowatts and stops there has told you about the machine and nothing about the joint.
We do not print a joint count per module. It is a property of your busbar layout and your series configuration, and a number carried over from somebody else's module is worse than no number.
Everything above is quoted for the station welding on the carrier, in line. The same figures on a machine that welds modules brought to it by hand describe a different situation, because half of what makes them repeatable is that the module never moved.
Gantry frame and machine body of the in-line welding station
Rendering — the station body
Scanner head carried on the gantry above a module
Rendering — the scanner on its axis
Module top face with busbars joined after welding
Rendering — the joints, made

≥1000 N is the figure buyers trust and the one you cannot re-check

This is the part of a welding specification that decides how the station gets accepted, so it gets the long answer instead of a table row. Everything else on this page follows from it.

  • 01 · Why this figure

    A pull figure is the only published number that describes the joint doing its job

    Depth and width describe the shape of the fusion zone; ≥1000 N describes what happens when somebody loads the busbar. That is why it is the first number an engineering department asks for, and the last one a brochure explains.
  • 02 · What it costs to obtain

    The joint is gone once you know the answer

    A pull test loads the busbar until the joint gives up. The joint is destroyed whether it passes or fails, and the module it belonged to does not go back on the line. 100% pull testing is not an inspection plan; it is a scrapping plan — which is exactly why it has to be designed rather than promised.
  • 03 · What runs at takt

    The station holds the conditions under which 1000 N was proved

    Per joint, in line, what is controlled is the parameter set and what is checked is the fusion geometry — ≥1.0 mm deep, ≥1.5 mm wide. Strength is established on samples against your busbar and your terminal, and the line's job from then on is not to drift away from the state that produced it.
  • 04 · Why the three are one argument

    Geometry is the daily evidence, strength is the periodic proof

    Read separately they look like three claims. Read together they are one method: prove strength on a sample, lock the parameters that produced it, and verify per joint that the fusion still has the shape those parameters make.
  • 05 · When a sample fails

    A failed pull sample is a parameter question, not a re-weld question

    The honest response is to bracket back to the last passing sample, quarantine what ran in between, and find what moved — fixture, material lot, surface condition. Re-welding a joint that already has fusion under it does not repair the joint; it adds heat to a module you have not yet diagnosed.

Why an under-made busbar joint is dangerous rather than merely weak is argued once, on the equipment page, and is not repeated here.

Busbar terminal joint seen close up on a prismatic module
Rendering — the joint the figure is about

Take this to any supplier

"How is your joint-strength figure obtained, on how many joints, and what happens to the module each of those joints came from?"

— What that answer has to contain

  • The sample basis — which joints, on whose parts, at what settings
  • Who agrees the frequency, and when it is written down
  • What is checked per joint instead, and against which figure
  • Where the destroyed sample goes on the day it fails

The pull test is a bench operation beside the line, not a station on it

Nothing inside the welding station pulls anything. Samples are taken off the line and loaded on a test bench, which is why the frequency is a production decision rather than a machine setting — and why it can be changed later without touching the station.

Depth and width are one criterion written as two numbers

≥1.0 mm and ≥1.5 mm are not two independent targets. They describe the same fusion zone from two directions, and a joint can miss the criterion by meeting only one.

GeometryWhat it rules out
≥1.0 mmFusion depth A joint that is wide on the surface and shallow underneath — the one that looks finished, passes a visual check, and carries current through a fraction of the section it appears to.
≥1.5 mmFusion width A joint that reached depth in a track too narrow to spread load — enough metal joined, in the wrong shape to hold the busbar when the pack is handled or vibrated.
50–100 mm/sThe speed that produces both Travelling too fast for depth or too slow for width. The window exists because the two requirements pull in opposite directions; where your joint sits inside it is set with your material, not before it.
Both figures are minimums, and minimums are what an inspector can work with. A criterion written as "good fusion" cannot be failed, which is another way of saying it cannot be passed.
We do not publish a materials table pairing busbar alloys and thicknesses with settings. Those pairings are established against samples of your parts during commissioning, and a table printed before that is a table about somebody else's parts.
Terminal and busbar surface after welding, seen from above
Rendering — the surface a visual check sees

The station is told where the joint is. It does not search.

Every accuracy figure quoted anywhere on this line is quoted with respect to a datum. On this station the datum arrives with the module, and what that buys and costs is worth stating plainly.

  • The module arrives located on its carrier, not placed by hand
  • Terminal positions have been confirmed at the addressing station upstream
  • The busbar plate and CCS are seated flat, not nearly flat
  • Joint positions come off your module drawing, not off a sample module
  • It does not correct a stack that was pressed out of square
  • It does not compensate a busbar plate that is sitting proud
  • It does not decide the joint layout — that is your module design
  • It does not re-find a module that arrived approximately

This is not a disclaimer; it is the reason the numbers above are worth anything. A station that has to find the part again before it welds is a station whose repeatability figures describe its search, not its weld. Ours are quoted for a part that arrived where the station was told it would be — which is what conveying and positioning exists to deliver.

Module arriving located on its carrier at the welding position
Rendering — located, then welded
Busbar plate and CCS seated flat on the module top face
Rendering — seated flat, not nearly flat
Welding head aligned over the joint positions it was given
Rendering — told, not searching

Send the busbar layout and one module drawing

Joint positions, busbar section and material, and whether your module is single-row or double-row. That is enough to say what this station would be quoted as, and whether you need it at all.

Reply within 24 hours / If hand welding is the honest answer for your volume, we will say so

Single-row and double-row modules run on the same station

That is a published capability and it is worth reading precisely, because "universal" survives contact with a quotation only if somebody says which parts of the station change and which do not.

What a row change movesWhat it does not move
The joint map the station is given — how many joints, where they sit, in what order they are welded The station itself: gantry, scanner and source are unchanged by row count
The fixture that presents the module, cut against your module envelope The published criteria — ≥1.0 mm, ≥1.5 mm and ≥1000 N do not soften because there are two rows
Cycle content at this station, because the number of joints changed Your takt, which is set by the slowest station in the segment rather than by this one
Read "single-row and double-row" as the station is not the thing that stops you, not as "no engineering required". The fixture and the joint map are still cut against your module, and that is true of every station on this line.
We do not publish a cycle time for this station on its own. A per-station figure invites a comparison against line takt that it cannot survive, and takt is published per tier where it belongs. Tier selection →
Single-row prismatic module on the assembly line
Rendering — single row
Double-row prismatic module of the kind the same station welds
Rendering — double row
Carrier fixture that presents the module to the welding head
Rendering — the part that is cut for you

6 kW is headroom, and headroom is what a window is made of

The joints on a blueprint module do not need everything a 6 kW source can deliver. That is the point, and it is worth a paragraph rather than a bullet.

A rating is sized for the worst part you will ever run

Busbar section and alloy differ from project to project, and copper is unforgiving about how much of the beam it accepts. A source sized exactly to the blueprint joint is a source that has already decided your product will never change.

Headroom is what lets speed stay a window

Section 07 called 50–100 mm/s a window rather than a setpoint. The window only exists if there is power in reserve — otherwise every harder joint has to be bought back with time, and time at this station comes out of the segment.

More power is not a better weld

Past the point where the joint is properly made, additional energy goes into heat the module has to absorb, spatter that station 14 has to clean, and distortion in parts that were pressed flat on purpose. Capability is a ceiling to work under, not a target to reach.

Which is why the honest way to read a 6 kW line item is as an envelope, not an achievement. It tells you what the station can still do when your busbar turns out to be thicker than the one in the drawing — and that is a question every project eventually asks.

Laser source and control cabinet alongside the welding station
Rendering — the source, cabinet side
Welding enclosure open at the working position
Rendering — where the energy goes
Post-weld cleaning and inspection position downstream
Rendering — station 14, cleaning up after it

Four numbers you will want that this page leaves blank

Each blank has a different reason, and none of them is that we do not know. Writing them down is more useful than filling them with figures that would describe another customer's module.

Sampling frequency for the pull test

How often a joint is destroyed to prove the rest depends on your joint count, your busbar material and what your own customer's specification demands. It belongs in your acceptance document, not in a brochure — and it is the first thing we will want to agree.

Joints per module

A property of your series configuration and busbar layout. Carried over from another module it is not a specification, it is a guess with a decimal point.

Cycle time for this station alone

Real, but only against a joint count and a joint map. Published on its own it becomes a number people compare across suppliers who each assumed a different module.

A settings table by material and thickness

Established against samples of your parts during commissioning. Printed in advance it would be a table about somebody else's parts, and the only thing it would reliably do is make this page look more complete than it is.

Four blanks with four different reasons is a specification; four blanks with one excuse is a brochure. Each of these is answerable — three of them with your drawing, and the fourth with your parts on our machine.

Control cabinet and operator panel of the welding station
Rendering — where the parameter set lives

What is delivered besides the station itself

A welding station that arrives without the argument for its settings is a station your process engineer has to characterise again. These three things travel with ours.

01

The sample basis, in writing

Which joints were pulled, on which parts, at what settings, and what they held. This is the document the ≥1000 N figure lives in — not this page.
02

The locked parameter set

The settings that produced those samples, recorded as the state the station returns to. Drift is only detectable against a state somebody wrote down.
03

Installation, commissioning and training

Including the acceptance run against the criteria above, and the handover of what an operator has to check and what only a sample can answer.

None of this is unusual, and that is the point: it is what separates a station you can accept from a machine you have to characterise yourself. Ask any supplier for these three and the answers will tell you more than the datasheet did.

Acceptance run at the welding position with the enclosure open
Rendering — the acceptance run
Operator station beside the welding cell
Rendering — what an operator checks
Post-weld inspection position on the module line
Rendering — station 14, the day after handover

Four questions that separate a welding station from a laser

None of them needs a drawing to ask, and all four can be put to any supplier — including us — before anything is committed.

Ask thisWhat a real answer sounds like
Which of your published figures are acceptance criteria? Two of them, and here is the document they go into. A supplier who says "all of them" has not thought about how the strength figure is obtained.
How is the strength figure proved, and how often? On samples, at a frequency agreed with you, against your busbar. ⚠️ An answer of "every joint is tested" is either wrong or expensive beyond belief.
What does the station receive, and from where? A located module and confirmed terminal positions. If the answer is that the machine finds the joints itself, ask what happens the day it finds the wrong one.
What changes when my module changes? Fixture and joint map. If the answer includes the criteria, the criteria were never criteria.

Our four answers are on this page: two of four; on samples against your parts at an agreed frequency; a located module with confirmed terminals; and fixture plus joint map, with the criteria unchanged. Everything above was written so those four can be checked rather than trusted.

Welding station seen alongside the stations either side of it
Rendering — the station, with its neighbours

Send the busbar layout, and we will send back a scope

Joint positions, busbar material and section, row count, and the module drawing they belong to. Four inputs, and the station is specified from them rather than from a catalogue.

What comes back

A station scope for your joint map, the fixture that has to be cut for it, and a plain statement of what would be proved on samples versus checked per joint.

If the answer is that you do not need this station

Below a certain volume and joint count, hand or semi-automatic welding is the better buy and we will say so. It costs us a line item and saves you a capital decision.
Busbar joints along the top face of a finished module
Rendering — the joints this page is about
Phone / WhatsApp
Address
Wuhan, Hubei, China
Response
Reply within 24 hours
Finished module after welding, ready for inspection
Rendering — after station 13
Welding station standing ready for its acceptance run
Rendering — the station on your floor
Module and pack assembly line seen along its full length
Rendering — seventeen stations, and this is one of them